    We are working with supplier that get our prt and asm file to modyfy.
    Supplier doesnt have intralink but use our templates.

    Now we want to check in supplier work to Intralink but some of
    assemblies have new file name and are using some old components that
    was not modified and are already in Intralink.

    New complete asm have new number.
    What will happen if we will check in only new files?

    How to do it best?

    It is all about 1000 files.

    Best regards
    Mathew
     
    mietek_kot, Jan 6, 2006
    #1
  2. mietek_kot

    Bruin Guest

    Are the assemblies/components/drawing (all objects) following your naming
    convention? Not following a naming convention of some sort gives me the
    chills.

    Import the assemblies into your workspace. The problem (I think) is old
    components that you import will show up as "new" objects. You should (I
    think) update all the existing components first. Then set the parameters
    of the new objects & check the new objects. Yes, a big job but unless
    someone has a better idea, that is how I would do it. You might be able to
    update all objects & only the objects that are already in Commonspace will
    get updated. I would have to experiment, but I think that would work.
     